What is certification lag in construction?
Certification lag in construction is the number of days between a contractor submitting an RA bill and the client certifying it, a wait that comes before the invoice and so sits outside receivables and a DSO measured from the invoice date.
Last reviewed
What does certification lag mean for an RA bill?
The bill exists, the work is done, and nothing can be invoiced until somebody signs. Because no invoice has been raised, the wait sits outside receivables, outside a DSO measured from the invoice date and outside the ageing report.
How is certification lag calculated?
certification lag = date certified - date submitted
Measure the median and the P80. A median of 11 days with a P80 of 34 is a different problem from a median of 11 with a P80 of 14.
Certification lag: a worked example
One sample RA bill, taken from the RA bill example in the process mining definition (2026 sample).
- RA bill submitted
- 8 Mar
- Sent back for correction
- 19 Mar
- RA bill resubmitted
- 22 Mar
- Certified
- 2 Apr
- Certification lag
- 25 days from the first submission; 11 days if measured from the resubmission
Sample dates, not a customer result. Measured from the resubmission, the same bill reports 14 days less, because the rejected pass drops out.
Why does certification lag matter?
On an EPC order-to-cash process this wait comes before the invoice, so it is one stretch of the cash cycle that receivables and a DSO measured from the invoice date do not cover. Part of it can be shortened by fixing what gets submitted, rather than by asking the client for anything.
Where does certification lag mislead?
Certification lag is a measure, not a contractual term; a contract will talk about a certification period or a review window instead, so check your contract for the terms that apply to you. And a resubmitted bill can carry only its new date, which erases the rejected pass and makes the lag look shorter than it was.
What do people get wrong about certification lag?
- Measuring from the resubmission
- The clock starts at the first submission. Measured from the last one, a bill that took thirty two days across three passes reports as twelve.
- Treating it as the client's problem
- Part of certification lag can come from what was submitted: a missing measurement sheet, an unagreed rate, an unapproved variation. Those can be fixed without a conversation with the client.
What else do people ask about certification lag?
How do you calculate certification lag?
Subtract the date the RA bill was first submitted from the date it was certified. In the sample bill above, submitted on 8 March and certified on 2 April, the lag is 25 days. Track the median and the 80th percentile (P80) across bills, not one bill, because a single bill can mislead.
Is certification lag the same as DSO?
No. Certification lag runs from RA bill submission to certification, which comes before an invoice is raised, so a DSO measured from the invoice date does not include it. Contractor DSO measured from work completion does include it; read the definition of contractor DSO for the difference.
How does Crestline measure certification lag?
Crestline keeps every rejected submission in the trail, so a bill that went round twice shows both passes and the lag is the real elapsed time rather than the last attempt.
Read where cash is stuck in a construction project and how to find it