Skip to content
Crestline
Construction & EPC

What is variation order?

A variation order is work outside the original contract scope that the client has instructed, priced and agreed separately — and until it is agreed, it is work being done for nothing.

Also called change order, VO, EOT claim.

Variation order in plain words

Variations arise constantly: a design change, a site condition, an instruction given verbally on a Tuesday. Each needs to be notified, priced, agreed and then billed, and each of those steps has its own queue.

Variation order: a worked example

One variation, from instruction to payment.

Instruction given on site
11 Feb · recorded in the site diary only
Notified formally
4 Mar · 22 days later
Priced and submitted
19 Mar
Agreed by client
28 May · 70 days in negotiation
Billed in the next RA bill
12 Jun
Instruction to billing
121 days, with work executed from February

The cost was incurred in February. Only the entitlement was missing, and it was missing for four months.

Why does variation order matter?

Unagreed variations are the quietest form of trapped cash on a project. The cost has already been incurred; only the entitlement is missing.

Where does variation order mislead?

A variation's real clock starts at the instruction, which often exists only in a site diary or an email. Measured from the day it entered the system, the delay looks like weeks when it has actually been months.

What do people get wrong about variation order?

Starting the clock at formal notification
The instruction usually exists weeks earlier in a site diary or an email. Measured from notification, months of exposure disappear.
Executing before the variation is agreed
Common and sometimes unavoidable, but it converts a pricing conversation into a claim. The figure worth watching is the value of work executed against unagreed variations.

How does Crestline measure variation order?

Crestline tracks variations as their own cases and, where the instruction date exists in any system, measures from it rather than from the day the claim entered the workflow.

30-minute discovery call

See your own variation order, measured from your ERP.

Thirty minutes, read-only. Bring one question about your project cash and we will answer it from your own data — or tell you we cannot.

Book a 30-min callEmail us