What is a BOQ (bill of quantities)?

BOQ is the short form of bill of quantities: the itemised list of every piece of work in a contract, with its unit, its quantity and its rate, and the price list every later bill is measured against.

Also called BOQ, BoQ, bills of quantities, schedule of quantities.

Last reviewed

Bill of quantities in plain words

Each line is one item: say, M25 concrete in footings, in cubic metres, at an agreed rate. Quantity times rate gives the line value, and the lines add up to the contract price. Every running bill is built from the same lines, so the BOQ decides what can be billed and at what rate.

How is bill of quantities calculated?

line value = quantity × rate; contract price = sum of line values

On an item rate contract the quantities are estimates and the rates are fixed. On a lump sum contract the BOQ is often only a way to split the price.

Why does bill of quantities matter?

A bill can only claim what a BOQ line allows. Work that fits no line becomes a variation, and a line executed beyond its quantity becomes a deviation, and both slow certification.

Where does bill of quantities mislead?

Whether quantities are re-measured or fixed depends on the contract type, so the BOQ is not binding in the same way everywhere. Read the contract's measurement clause before treating a BOQ quantity as a limit.

What do people get wrong about bill of quantities?

Billing an item that has no BOQ line
It will be sent back, or paid as a variation after a negotiation. Raising the variation first is faster than defending the bill.
Treating estimated quantities as guaranteed work
On a re-measurement contract the contractor is paid for what is measured, not for what the BOQ listed. A BOQ quantity is a forecast, not an entitlement.

What else do people ask about bill of quantities?

What is a rate only item in a BOQ?

A rate only item is a BOQ line marked "rate only" in place of an amount: the bidder quotes a unit rate but no quantity is given, and the rate is the basis of payment for whatever quantity of that work is later measured. Tenders use it where little or none of the work is expected, or where it is an alternative to another item. How rate only items are paid and how they count when bids are compared depend on the tender, so read its conditions.

What is a priced bill of quantities?

A priced bill of quantities is a BOQ with the bidder's rates and amounts filled in against each line. The unpriced BOQ is issued with the tender, the priced BOQ comes back with the bid, and the accepted one becomes the price list every RA bill is measured against.

What is the difference between a BOQ and an RFQ?

A BOQ (bill of quantities) lists the work items, units and quantities a contract covers, priced by the bidder. An RFQ (request for quotation) is a buyer's request to suppliers to quote prices for stated goods or services. A contractor may send RFQs to vendors to price the materials behind its own BOQ rates.

How does Crestline measure bill of quantities?

Crestline matches each RA bill line to its BOQ line, so a bill that exceeds a quantity or uses an unlisted item is flagged before it goes to the client.

The order-to-cash lens
30-minute discovery call

See your own bill of quantities, measured from your ERP.

Thirty minutes, read-only. Bring one question about your project cash and we will answer it from your own data or tell you we cannot.

Book a 30-min callEmail us